Works included:
Demolishing existing cake barn bay division walls,
Erection of a reinforced concrete push wall approximately 4m high,
Construction of a 4m deep wet well, using a cofferdam temporary works system,
Supply and install ductile iron pipework to feed the wet-well in preparation for a new filtrate and SAS line,
Installed a reinforced concrete floor slab to accommodate a new processing barn,
Installed all associated duct work in preparation for new screw conveyors and separation units